(403) 689-1599

  • Home
  • About Us
  • Our Proven Process
  • Services
  • Brownfield/As-built
  • Greenfield
  • Contact
  • Careers
  • More
    • Home
    • About Us
    • Our Proven Process
    • Services
    • Brownfield/As-built
    • Greenfield
    • Contact
    • Careers

(403) 689-1599

  • Sign In

  • My Account
  • Signed in as:

  • filler@godaddy.com


  • My Account
  • Sign out

Signed in as:

filler@godaddy.com

  • Home
  • About Us
  • Our Proven Process
  • Services
  • Brownfield/As-built
  • Greenfield
  • Contact
  • Careers

Account


  • My Account
  • Sign out


  • Sign In
  • My Account
Valor EPC

 Water Injection Pump Building & Cavern Wash Pump Building 

Water Injection Pump Building & Cavern Wash Pump Building

Turnkey Packaged Solution

  Project Background:

  • New waste water disposal and storage facility in remote location requiring a cavern wash pump building and a disposal injection pump building.
  • Project executed in partnership with DistributionNOW pump division. 


Solution & Execution:

  • DNOW specified and procured the pumps and associated equipment.
  • Valor developed the P&ID’s from client’s plant process conditions.
  • We designed the pump skids using 3D software to have regular reviews with the client to ensure constructability, operability, access and egress.
  • Communication and integration with fab. shop to ensure IFC drawings were fabrication ready (can be built, all materials and welding details shown).
  • Fabrication support to work through shop issues as they arose. 


Final Results:

  • Fully reviewed and approved design with all client stakeholders ensuring all parties would work together to get the project done effectively.
  • Properly selected pumps and lines sized as per process conditions provided.
  • Water injection pump building designed to allow for two future pumps.
  • Successful integration with fab. shop to minimize RFI’s.
  • Two complete skidded buildings were shipped to site to minimize field work.

Project Highlights:

  1. From concept to IFC in 5 weeks
  2. No resources sitting idle – all contractors come and go as req’d = less than 2 FTE’s over the 5 week job span
  3. Integrated with fab shop so drawings produced hit shop floor and can be built (no additional fab details req’d)

our proven process

“The facility ended up being the cheapest site we have built in 7 years in the Powder River Basin, looking at engineering + construction costs.  We were really pleased with the work that Valor produced and accomplished the goal of cutting overall facility costs.”


Project Manager, EOG Resources